Illustrative flexible grid connection study

Could this data centre bring capacity online earlier?

Explore a 3D data-centre campus, the controller, battery sizing, and the potential value of an earlier grid connection.

ILLUSTRATIVE NET VALUE OF EARLIER CAPACITY
€0Estimated contribution after modelled battery and integration costs. Not electricity savings.

Illustrative estimates, not verified customer savings or an approved grid offer.

Request a site study
EXAMPLE STUDY · PREPARED FOR
Illustrative data-centre operatorEurope · illustrative
Loading the interactive 3D campus…
NORMAL IMPORT10 MW import
FACILITY2 hall units · 10 MWBATTERY0 MW dispatch
Could a flexible connection bring capacity online earlier?

Architectural concept visualisation, not the named prospect's actual buildings or an operating customer installation.

GridPassSIZE · CONTROL · PROVE
Extra conditional grid capacity
2.0 MW
Above the firm grid tranche
Full-event meter compliance
PASS
0 minutes above the cap
Minimum battery estimate
5.0 MWh
With approved flexibility, initial SOC and reserve
Gross earlier-capacity contribution
€2.46m
Illustrative, not booked revenue or direct energy savings

Meter-level controller twin

A minute-resolution demonstration of the full curtailment event and recovery. Battery is dispatched with approved cooling relief; essential loads remain protected.
READY
GRID / CONNECTION10.0 MWContracted cap 8.0 MW in event
GRIDPASS CONTROLLERSTANDBYBattery discharge 0.0 MW
DATA CENTRE10.0 MWProtected IT + cooling + facilities
Battery SOC 90%Cooling relief 0.0 MWApproved compute relief 0.0 MWMeter headroom —
Site demandGrid meterEvent limitBattery discharge
T−30 min

Feasibility & sizing

Checks the full event, not just first-second response.

Peak site demand / event cap10.0 / 8.0 MW
Available approved relief0.4 MW
Minimum battery, no other relief6.2 MWh
Minimum battery, with relief5.0 MWh
Worst logged meter exceedance0.00 MW
Minimum observed battery SOC34%
Check outcomeFull event: PASS

Evidence log

Synthetic event record; download the meter trace as CSV. Production would use signed, time-synchronised logs.

The early-connection business case

Compare the firm-only tranche with a proposed flexible tranche until full firm capacity arrives.

ASSUMPTIONS, NOT A QUOTE
Illustrative net contribution from the earlier flexible tranche
€850k

Conditional on accepted flexible access and commercially occupied IT capacity. Excludes financing, taxes and unmodelled penalties.

Earlier availability24 months
Flexible IT equivalent1.6 IT MW
Potential battery right-sizing€310k
Gross contribution from earlier IT capacity€2.46m
Incremental dedicated BESS CAPEX−€1.50m
Controls / metering / integration (budget)−€100k
Battery losses & cycling (modeled period)−€6k
Modeled gross less incremental costs€850k

Battery right-sizing compares required nameplate MWh with and without approved cooling/compute relief; it is a comparison against an all-battery design and must not be added again to the net result. The gross commercial contribution comes from IT capacity made usable earlier, not electricity bill reduction. GridPass cannot promise accelerated connection without a utility offer or validated control capability.